Madrid Metro to close 24 stations for rail system upgrade work this summer

Work will affect around 80,000 passengers, who will be provided with alternative services

In its biggest maintenance project for a decade, the Madrid Metro will temporarily close 24 stations on five lines over the summer so that workers can reinforce rails and foundations along 34 kilometers of track.

The three-month venture, which gets underway this week on some lines, will affect about 80,000 passengers, who will have to rely on alternative routes or take replacement bus services provided by Metro authorities.

Around €26 million has been earmarked for the so-called “Operation Tunnel” project – almost three times the €10 million allotted to summer maintenance programs over the past three years.

Government officials hope to introduce Operation Tunnel on an annual basis to upgrade the infrastructure throughout the capital's underground rail network. Work in the Metro usually takes place during the summer months when many people are away on holiday and there is less passenger traffic.

The routes that will be affected this year are: Lines 5 (light green), 6 (circular, gray), 7 (MetroEste, the newest route), 10 (royal blue) and 12 (MetroSur). 

Line 10. On June 24, the stretch between Puerta del Sur and Colonia Jardín stations will be closed for about two months as workers replace rail dowels and rebuild the concrete foundations that hold them, as well as improving water drainage systems.

Line 6. Work on the route between Moncloa and Metropolitano stations will begin on June 26 for about two months, but only Ciudad Universitaria station will remain closed right through until September 1.

Line 5. Work on the link between Alameda de Osuna and Torre Arias stations will begin on August 2 and will last about two weeks.

MetroSur. Resolving water leakage and ensuring trains do not derail as a result of drainage problems are two priorities on this line, which was opened in 2003. Two years ago, two stretches of the line were closed as emergency precautions. This summer, work will affect around 14 kilometers of track.

MetroEste. The newest of all the rail lines, inaugurated in 2007, this route has also been plagued by leakage problems from water with high salt content. Work will take place for three months and during that time services will be suspended between Estadio Olímpico and Hospital del Henares stations. The exact dates have not yet been worked out by Metro officials.

Y ADEMÁS...

Comentar Normas

Para poder comentar debes estar registrado en Eskup y haber iniciado sesión

Darse de alta ¿Por qué darse de alta?

Otras noticias

Últimas noticias

Ver todo el día

Ros gana las elecciones en Lleida con los peores resultados del PSC

Los socialistas pierden la mayoría absoluta y pasan de 15 a ocho concejales

El PSE se sostiene

j. m. g. Bilbao

Vuelve a perder votos, sobre todo en Álava, pero aguanta la irrupción de Podemos y añade nuevas alcaldías

Mayorías absolutas para 14 alcaldes gallegos imputados

Cristina Huete Ourense

Un total de 22 regidores acudieron a las urnas bajo el peso de acusaciones judiciales

EL PAÍS RECOMIENDA

Dar de comer a la humanidad: desafío y formidable negocio

En 2050 se necesitarán 83.000 millones anuales para alimentar a 9.600 millones

¿Recuerdas cuando éramos capaces de leer de corrido?

Ana Carbajosa Madrid

Los efectos de la exposición a Internet despierta preocupación entre científicos

Lo más visto en...

» Top 50


Webs de PRISA

cerrar ventana